Transmission owners asked FERC to back 10 to 20 year contracts, with PJM-area utilities seeking 80% payment commitments backed by collateral. We see a second layer of cost terms for large loads.
A Harvard study of 403 hyperscale sites found 82 TWh of use, 1.8% of U.S. electricity, through April 2025. The fleet has more than doubled since, so we read the figure as a floor.
AI training clusters swing load in sync and can drop offline during grid faults, pushing utilities to ask for storage and fast inverters. We expect ride-through rules in more interconnection deals.
Ratepayer advocates want Wisconsin to return to state-led energy planning as utilities propose new plants for data centers. We track integrated planning as a lever on who pays for new load.
DC Blox filed a DRI notice for a 500,000 sq ft third building at its 100-acre Douglas County, Georgia campus, planned for 200MW total. The first two buildings are leased.
An Odessa, Texas AI campus pairs $750 million in financing with a first 65 MW phase ordered for the first half of 2027, for an unnamed frontier AI lab. West Texas keeps drawing power-first builds.
Meta's land arm filed a site plan for a 350-acre Ohio site next to a proposed 500 MW gas plant that would power it. The hearing is Nov. 23. We see co-located generation becoming the default ask.
Northwest Pipeline's 24-inch Silver Spur would add about 275 MMcf/d of firm capacity into Idaho. Comments are due Dec. 14. We note new Mountain West gas capacity for siting screens.
FERC is set to decide Thursday on a certificate for Mountain Valley's 136,900 hp Swann compressor station, while Virginia air permitting stays stalled. We read Boost as a Mid-Atlantic gas test.
GE Vernova and Siemens Energy report record turbine orders and growing backlogs despite post-midterm scrutiny of data centers. We treat turbine slots as a gating item for gas-backed sites.
The Ohio Power Siting Board meets Nov. 19 on two plants for hyperscale data centers, including a 1,350 MW behind-the-meter unit in Millersport. We see behind-the-meter gas scaling in Ohio.
Blue Owl closed a 54MW Gainesville, Virginia building for about $779.5 million, fully leased to one hyperscaler, part of a 198MW, three-building deal. That is roughly $14.4 million per MW.
Hartford, Illinois planners postponed zoning for a 378-acre campus with no named operator. The landowner pitched a $3 million payment and per-MW fees. Speculative land faces more questions.
Opelika planners recommended a technology overlay on about 500 acres along I-85 in Alabama over opposition from 200-plus residents. No data center deal is pending. The city council decides next.
A Florida-based company secured an option on nearly 90 acres in Union County, Arkansas to expand an AI campus near El Dorado. We log options as the early signal in land assembly.
Augusta planners hear a request Nov. 23 to rezone about 383 acres near the regional airport to data center use for a seven-building campus. The full commission makes the final call.
A bipartisan House bill, with a Senate companion, would have DOE give communities technical help and independent analysis of data center proposals. We expect better-informed local reviews.
A charter amendment cleared to gather signatures would bar Columbus data centers needing 25 MW or more. Over 20 Ohio restriction measures passed this month. We treat Ohio ballots as a siting risk.
Umatilla and Umatilla County asked a court to restart state permit work, citing more than $1.2 billion in stalled investment. We watch whether a governor's pause holds up in court.
Arizona's Proposition 207 requires compensation when land rules cut property value; Phoenix landowners sought $750 million after 2025 limits. We see entitled land holding value in Arizona.
Moreno Valley, California unanimously adopted a 45-day ban and directed staff to draft a permanent one, after striking a 100 MW threshold. We see Southern California inland sites narrowing.
Hillsboro, Oregon extended its July land use moratorium on data centers by six months while it rewrites its development code. Oregon now has pauses at both state and city levels.
With Democrats taking full control in 2027, Minnesota lawmakers plan to target utility returns on equity and data center costs. We expect large-load tariffs to stay on state agendas.