PJM, CAISO, NYISO and others filed large load rules at FERC on Nov. 16. PJM would study load and generation together in one year, about twice as fast. We read it as a shorter path to power.
Google agreed to buy 50 MW from Quaise's Project Obsidian near Newberry Volcano, with delivery as early as 2030 and no price disclosed. We track firm clean supply as a siting input.
Orennia puts 191 GW of planned data center capacity at new risk after the midterms, concentrated in Texas, Ohio and Georgia. We expect utilities to tighten large load collateral.
Draft reports would keep 11 gas and oil plants open up to three years, to 2033, and flag downstate shortages as soon as 2027. We expect more retirement delays where load outruns supply.
Giga Energy signed a 10-year, $1 billion lease with an unnamed AI cloud provider for 60 MW on about 30 acres in Hunt County, Texas. Service is due in spring 2027.
Blue Owl's trust bought a 363,220 sq ft Gainesville, Va., facility fully leased to one hyperscaler, backed by a $512.6 million Citibank and Wells Fargo mortgage.
Patmos plans to convert a former Walmart in Fairfield, Ala., into a 20 MW campus that could grow to 50 MW, and says it will pay Alabama Power's full cost to serve.
HSBC sold about $300 million of the $18 billion Project Miner loan for Oracle's New Mexico campus in the mid-80s. We watch construction debt pricing as a read on project risk.
SpaceX proposed a $50 billion campus on nearly 750 acres near Willcox Playa and says it would spend over $3 billion on grid upgrades. Local groups are organizing to stop it.
EOG approved $300 million to take its Janus plant in the Delaware basin from 300 to 600 MMcfd by late 2028, citing tightening processing capacity as takeaway grows.
The Nov. 10 ruling keeps the permit for 41 gas turbines, about 1.2 GW of behind-the-meter power, in place. We count onsite gas as a live path to power for large campuses.
Decatur, Ill., council voted 6-1 to let a developer run a gas pipeline under Lake Decatur, a project estimated at $115 million with more than 600 construction jobs.
Records show an OpenAI affiliate paid $773.6 million for about 1,440 acres at the Savannah Gateway Industrial Hub in July, roughly $537,000 an acre. A key comp for the Southeast.
Amazon Data Services paid $72 million for 13 acres on Hazel Park Court in Chantilly, about $5.5 million an acre. We log it as a Northern Virginia land comp.
Alaska approved a 50-year lease offer to STAK Energy for 715.4 acres on the North Slope, allowing up to 3 GW of onsite gas generation. Financing and other permits are pending.
Prologis sued Trenton, Ohio, in federal court after about 80% of voters approved a 25 MW cap on Nov. 3. We watch vested-rights cases like this one closely.
A Tribune analysis found at least $1 billion in local property tax rebates across 53 agreements at 34 data centers, guaranteeing 465 jobs in total. Expect incentive scrutiny.
Aurora's mayor proposed a moratorium through 2027 everywhere except one area north of I-70, plus home buffers and no new tax incentives. Council takes it up by early December.
North Carolina's new large load tariff makes data centers post an upfront deposit covering new plants, lines and hookups, not just connection costs. We expect more states to copy this model.
Oregon regulators approved tariff changes that make new data centers in Pacific Power's territory pay the full cost of service through direct contracts and direct assignment.
DOE kept the 1,420 MW Campbell coal plant running another 90 days, to mid-February, after a court vacated an earlier order. Consumers reports $303 million in net costs through September.
Valor Energy closed a $3.6 million buy of a Youngstown bitcoin site with about 18 MVA from Ohio Edison and plans $700 million of AI buildout, with permits and financing still open.
A state filing lists a 341,326 sq ft shell in Hunt County starting Nov. 24 on land Core bought for about $232.5 million with roughly 430 MW of utility power. We see a bitcoin miner turning landlord.
AWS started work on up to nine buildings on 304 acres bought from NIPSCO, about half a mile from the Schahfer station. We read it as a utility land sale sited for the power next door.
Firmus had about 916 MW contracted and 46 MW running as of September, and is seeking $3 billion of equity plus customer prepayments. We watch prepayments become the standard neocloud funding tool.
NRG says the deal values one 1.2 GW Texas plant at about $1,400/kW while it builds new gas for just above $1,000/kW. We treat that gap as a marker for what existing gas capacity is worth.
Nevada regulators backed a nine-turbine plant at the Tahoe-Reno Industrial Center, fed by a new Great Basin lateral, with construction from Q1 2027 to 2029. We see self-supply skipping the queue.
Florida Gas Transmission sued 16 landowners who refused survey access for a 38-mile line, about 15 miles of it on U.S. Sugar land. We expect access fights like this to slow new gas laterals.
Diamondback is buying Double Eagle's Permian assets for about $5 billion on a view of strong regional gas growth and demand. We read more associated gas headed for in-basin power buyers.
Google asked Palo, Iowa, to annex about 650 acres, 550 of them south of the Duane Arnold nuclear plant, for up to six buildings. We note annexation moves the vote from the county to the city.
Pennsylvania Data Center Partners ended its sale agreements on 144 acres in Monroe Township that needed a zoning map change. We count rezoning-dependent farmland as the hardest sites to close.
A draft Ohio bill would add holders of Power Siting Board certificates for transmission or gas lines to the public utility definition, which legal experts say could open eminent domain for projects.
Oklahoma's AG wants to join a suit arguing Sand Springs had no authority to annex the roughly 826-acre Google site through a 1966 fence-line strip. We flag strip annexations as title risk.
Maryland leaders are expected to propose two to three year statewide moratoriums, with at least 15 counties already frozen. We treat Maryland as closed to new sites through the session.
A refiled Maine bill would halt data centers over 20 MW until Nov. 1, 2027, and the governor-elect backs a moratorium after the last one was vetoed. We watch for a January vote.
Louisiana's governor reads strong votes in data center and LNG parishes as a mandate to build more, while New Orleans works on its own rules. We see the state pulling away from the national trend.
H.R. 11002 would bar new data centers on Forest Service and Interior land and has 13 Democratic cosponsors. We read it as a sign that federal sites will stay contested.
Rochester's council voted 5-1 for a moratorium of up to a year while staff write definitions and rules. Staff say the city cannot ban data centers outright. We read pauses as rule-writing.
Broken Arrow pushed its six-month pause, which was due to end Dec. 31, to June 2027 to write siting, water and infrastructure rules. We expect most local pauses to run past their first deadline.
BIS now requires data centers, foundries and chip exporters to vet customers so export limits cannot be bypassed through data centers in third countries. We see more pressure to build compute at home.